Wednesday, July 30, 2008

What and How To Create Routing

You have to proceeds following steps:
1) CA01 - Create routing First screen = Material on which you have to create a routing Plant Second screen = Usage 1 if you create routing for production purpose. Status 4 release general Enter 2) Now go on to application tool bar and select operation Here you have to enter work center, control key and description For eg. w/c 1 plant pp01 description w/c 2 plant pp01 description plant pp99 goods reciepts 3) Now select the component allocation Select the material here and click on to the new assignemnt for assign the operation seqence on to the material.
4) SAVE
Now routing is create with routing group number .
What is meant by routing?
Routing is nothing but your Process Plan.
A routing is a description of which operations (process steps) have to be carried out and in which order to produce a material (product). As well as information about the operations and the order in which they are carried out, a routing also contains details about the work centers at which they are carried out as well as about the required production resources and tools (includes jigs and fixtures). Standard values for the execution of individual operations are also saved in routings.
Routings (generic) consist of the following objects:
- Routing - Rate routing - Reference operation set - Reference rate routing
Routings enable you to plan the production of materials (products)
In a routing you plan
- The operations (work steps) to be carried out during production
- The activities to be performed in the operations as a basis for determining dates, capacity requirements, and costs
- The use of materials during production
- The use of work centers
- The quality checks to be carried out during production